LOCATION: Darwin, NT
CLIENT: Charles Darwin University
VALUE: $1,153,349.00
STATUS: Completed April 2020
DESCRIPTION:
Scope Building were awarded the contract for the refurbishment of the Charles Darwin University Machine Shop in the Mechanical “Training Building (Purple 13). The works included are listed below:
- Certification
- Demolition
- Solar Span Panelling
- Thermal Insulation
- Mezzanine Flooring including stairs, balustrades and handrails
- New stud walls, suspended ceilings and internal linings
- Aluminium framed windows and ventilation louvres
- Vinyl Flooring
- Painting internal and external
- Perforated steel removable barriers
- Stainless steel bollards
- Electrical Works
- Communication works
- Mechanical Works
- Joinery
- Upgrade of fire services
- New Outdoor Shade Structure
- New outdoor table and chairs
The project was completed to a high standard within the varied contract time frames, there was no work safe issues.